Preparation before installation of cooling tower
1、 Preparation before installation
1. Before unboxing the electric motor, check whether the packaging is intact and undamaged, and whether there are any signs of moisture.
2. Check if the nameplate data of the motor meets the requirements.
3. Carefully inspect the motor for any deformation or damage during transportation, and check for loose or detached fasteners.
4. Measure the insulation resistance with a megohmmeter, and the value should not be less than 0.5 megohms. Otherwise, the stator winding should be dried, and the temperature during drying should not exceed 120 ℃.
1. When installing the product, the shell or bracket should have sufficient strength and rigidity, and the four feet should be leveled and kept horizontal before being tightened.
2. The hub of the fan should be well matched with the output shaft of the reducer, and the nut should be tightened.
3. After installation, the fan should be adjusted to the optimal state to ensure smooth operation.
4. The fan blades should be turned flexibly.
1. The shell or bracket of the product should have sufficient strength and rigidity during installation, and the four feet should be leveled and kept horizontal before being tightened.
2. The hub of the fan should be well matched with the output shaft of the reducer, and the nut should be tightened.
3. After installation, the fan should be adjusted to the optimal state to ensure smooth operation.
4. The fan blades should rotate flexibly.
5. Adjust the tightness of the belt
Article Address:https://www.trlen.com/news/757.html
Guangdong Trlon Energy-saving Air Conditioning Equipment Co., Ltd.
Contact:Mr. Wang
Free Hotline:4008-8383-95
Company Email:sales@trlon.com
Web Site:https://www.trlen.com/
Company Address: 1916A, Block A, David Donglong Business Building, Longhua, Longhua District, Shenzhen